The MaRS Phase 2 team achieved a major milestone this month—we have now “topped off” the building, which means the structure is complete!
Overall site progressFlying a form for the Level 22 slab
To give you a better idea of the amount of work that has been completed in the past year, here are some stats:
An average of 200 workers on site daily
Completion and opening of the new Queen’s Park TTC kiosk
Over 3,500 concrete trucks on site
Over 1,100 curtain wall panels installed
Over $110,000,000 worth of work completed
Countless hours spent by our general contracting and design teams co-ordinating and designing
Trade BBQ celebration on siteThe B+H Architects team at the Topping Off celebration
We at MaRS are incredibly proud of the team’s success to date and are looking forward to working together until the building is complete in September 2013!