The MaRS Phase 2 team achieved a major milestone this month—we have now “topped off” the building, which means the structure is complete!

MaRS Centre Phase 2
Overall site progress
MaRS Centre Phase 2
Flying a form for the Level 22 slab

To give you a better idea of the amount of work that has been completed in the past year, here are some stats:

  • An average of 200 workers on site daily
  • Completion and opening of the new Queen’s Park TTC kiosk
  • Over 3,500 concrete trucks on site
  • Over 1,100 curtain wall panels installed
  • Over $110,000,000 worth of work completed
  • Countless hours spent by our general contracting and design teams co-ordinating and designing
MaRS Centre Phase 2
Trade BBQ celebration on site
MaRS Centre Phase 2
The B+H Architects team at the Topping Off celebration

We at MaRS are incredibly proud of the team’s success to date and are looking forward to working together until the building is complete in September 2013!